hir-szivkorhaz-balatonfured

The two modernisation projects of the State Hospital of Cardiology, where CÉH Zrt. acted as drawing inspector and independent engineering supervisor.

Project I: Attending the drawing inspection and independent engineering activities of the project entitled “The energy efficient modernisation of the internal lighting, the cooling system, kitchen and laundry equipment of the State Hospital of Cardiology and integration of solar panels in the electricity subsystem” that was realised in the framework of the New Széchenyi Plan, supported by the European Union and co-funded by the Cohesion Fund.

Project amount: HUF 130,562,891.

Project II: Attending the drawing inspection and independent engineering activities of the project entitled “Improvement of the internal thermal protection of the buildings of the State Hospital of Cardiology, energy efficient reconstruction of the hospital’s boiler room and centralised heat supply system” that was realised in the framework of the New Széchenyi Plan, supported by the European Union and co-funded by the Cohesion Fund.

Project amount: HUF 319,279,580.